Pengendalian Waktu Pekerjaan Konstruksi Pembangunan RSUD Dr. Sobirin Kabupaten Musi Rawas

Analysis of Time Control for Construction Work for the Construction of Dr. RSUD. Sobirin, Musi Rawas Regency

Authors

  • Perri Putra Teknik Sipil Program Studi Program Profesi Insyinyur, Universitas Sriwijaya

Abstract

This paper comprehensively examines time control in construction projects in Indonesia, with a specific focus on the development project of the Regional General Hospital (RSUD) Dr. Sobirin in Musi Rawas Regency, South Sumatra. Effective time control is a crucial factor in the success of construction projects, especially for healthcare infrastructure projects that have a direct impact on public services. This paper explores various time control methods and techniques, specific challenges in the context of hospital construction in regional areas, as well as strategies and solutions implemented. The case study of RSUD Dr. Sobirin is presented to provide practical insights into the implementation of time control in the real-world context of healthcare facility construction in Indonesia.

Downloads

Download data is not yet available.

References

Dipohusodo, I. (2015). Manajemen proyek & konstruksi. Yogyakarta: Kanisius.

Ervianto, W. I. (2016). Manajemen proyek konstruksi. Yogyakarta: ANDI.

Hatmoko, J. U. D., & Khasani, R. R. (2020). Analisis keterlambatan proyek konstruksi di Indonesia: Studi kasus proyek infrastruktur pemerintah. Jurnal Teknik Sipil Institut Teknologi Bandung, 27, 1-10.

Husen, A. (2018). Manajemen proyek: Perencanaan, penjadwalan, dan pengendalian proyek. Yogyakarta: ANDI.

Mansyur. (2018). Analisis pengendalian waktu dan biaya proyek konstruksi dengan metode earned value. Jurnal Teknik Sipil Universitas Syiah Kuala, 1(3), 523-533.

Prianto, K. (2019). Implementasi metode critical path dalam penjadwalan proyek konstruksi. Jurnal Teknik Industri Universitas Muhammadiyah Surakarta, 20(1), 131-142.

Soeharto, I. (2019). Manajemen proyek: Dari konseptual sampai operasional. Jakarta: Erlangga.

Sudarto. (2017). Manajemen konstruksi. Bandung: Pustaka Setia.

Wibowo, A. (2017). Manajemen proyek konstruksi. Yogyakarta: ANDI.

Downloads

Published

2025-01-21

How to Cite

Perri Putra. (2025). Pengendalian Waktu Pekerjaan Konstruksi Pembangunan RSUD Dr. Sobirin Kabupaten Musi Rawas: Analysis of Time Control for Construction Work for the Construction of Dr. RSUD. Sobirin, Musi Rawas Regency. LITERA: Jurnal Ilmiah Mutidisiplin, 2(1), 154–168. Retrieved from https://litera-academica.com/ojs/litera/article/view/131